The following list presents the MTA's final program of projects for a portion of the Section 5307 funding from Federal Fiscal Year 2011. The projects have received federal funding in the Federal Transit Administration (FTA) grant NY-90-X674, executed May 29, 2012. The public hearings for the proposed program of projects were held by the Metropolitan Transportation Authority, on June 20, 2010. This list is provided to the public as required by 49 USC 5307.

Agency PIN Description Federal Local Total
LIRR L605/02/LB 12.64.01 Signal Normal Replacement Program $7,500,000   $7,500,000
LIRR L603/01/TB 12.24.03 2011 Annual Track Program 14,560,000   14,560,000
LIRR L605/01/L7 12.54.01 Atlantic Avenue Tunnel Cable Replacement 1,700,000   1,700,000
LIRR L607/01/AC 12.64.20 Signal Power Motor Generator Replacement 1,800,000   1,800,000
MNR 882315 11.71.12 NEWBURGH-BEACON FERRY CAP COST CONTRACT 942,344 $1,682,718 2,625,062
MNR 8TM015 11.71.12 HAVERSTRAW-OSSINING FERRY CAP COST 640,000 3,243,481 3,883,481
MNR M602-02-02 12.34.02 Fordham Station Imp. 6,000,000   6,000,000
MNR M602-02-06 12.34.02 New Haven Line Station - Ph. 2 16,610,000   16,610,000
MNR M603-02-11 12.24.03 HRLB Cable Replacement 8,000,000   8,000,000
MNR M604-01-02 12.64.01 West of Hudson Signal Imp. 11,047,656   11,047,656
MNR M605-01-07 12.24.03 Replace HRLB Breaker Houses 11,000,000   11,000,000
NYCT CM03-7161 12.44.05 East New York Shop Ventilation Improvements 7,776,000   7,776,000
NYCT CM03-7164 12.44.05 Rehab Power Centers 2 and 3,Coney Island Shop 13,710,000   13,710,000
NYCT CM09-7115 12.12.21 Purchase 300 B-Division R179 Subway Cars 121,613,759   121,613,759
NYCT MW01-6913 12.64.01 Signal Control Modifications, Ph 4,Systemwide 12,619,700   12,619,700
NYCT MW12-7070 12.43.05 Rehab and Flood Mitigation at 148 Street Yard 34,340,000   34,340,000
NYCT MW38-6838 12.64.01 Modernize Roosevelt Interlocking Qns Blvd Ln 115,520,000   115,520,000
NYCT PP02-7223 12.44.09 Security Hardening at 3 Locations 12,000,000   12,000,000
NYCT SI01-6628 12.34.02 Staten Island Station Structural Repairs 13,500,000   13,500,000
NYCT SI08-6941 12.24.03 Rehab 8 Bridges, Staten Island 18,360,379   18,360,379
NYCT ST04-6084 12.34.02 ADA: Forest Hills, 71st Ave Queens Blvd Line 33,440,000   33,440,000
NYCT ST04-6523 12.34.02 ADA: Kingsbridge Road, Concourse Line 21,980,104   21,980,104
NYCT ST04-6523 12.94.09 ADA: Kingsbridge Road, Concourse Line 6,779,896   6,779,896
NYCT ST04-6956 12.34.02 ADA: Hunts Point Ave, Pelham Line 27,105,000   27,105,000
NYCT ST22-0204 12.34.02 Station Renewal,Hunters Point Ave,Flushing Ln 8,909,503   8,909,503
NYCT ST22-7426 12.34.02 Station Renewal, 5 Locations, Myrtle Av Line 61,637,691   61,637,691
      $589,092,032 $4,926,199 $594,018,231