BW-15
CONSTRUCTION FOR BW-15 INSTALLATION OF NECKLACE LIGHTING, ACOUSTIC MONITORING SYSTEM ON THE MAIN CABLE AND INTERIOR TOWER LIGHTING AT THE BRONX WHITESTONE BRIDGE
$5M to $10M
Installation of new necklace lighting system on both cables at the BWB, including replacing all wiring and messenger cables and any necessary upgrades to the electrical service. In addition, the work includes the installation of an acoustic monitoring system on the main cable and installation of lighting within the tower interiors.
- Replacement of the Main Cable Necklace Lighting.
- Installation of a messenger cable on Main Cable
- Installation of an acoustic monitoring system on Main Cable
- Installation of lighting within the bridge towers
- Provide Maintenance & Protection of Traffic as required.
Duration of Contract 12 Months
MP-06
SUBSTRUCTURE & UNDERWATER SCOUR PROTECTION
$10M - $50M
Under this contract the contractor will perform all construction work associated with restoration of scour protection and the rehabilitation of substructure elements of the Marine Parkway Bridge.
- Coordinate with B & T and outside agencies for securing necessary documents and applicable construction permits.
- The contractor will conduct hydrographic survey prior to placement of the material in order to determine the mud line contours.
- Install pier scour protection counter measures to reduce the risk of scour and rehabilitation of unsound concrete on all substructure elements including pier caps and pier stems above high water, within the tidal zone and underwater.
- Provide Environmental Mitigation as required.
- Provide Maintenance & Protection of Traffic as required.
Duration of Contract 18 Months
QM-81
DESIGN AND CONSTRUCTION SUPPORT SERVICES FOR QM-81, CONTROLS/COMMUNICATIONS SYSTEM
$1M - $5M
Under this contract, the consultant will design for the replacement of QMT Facility Supervisory Control and Communications Systems on Tunnel Ventilation, Power, Signals, Variable Message Signs, Pumps and Lighting and other Tunnel Systems. Work will include: temporary relocation of the existing control room function along with reconstruction and refurbishing of the existing control room space in the service building as well as installation throughout the tunnel of new monitoring devices, communication equipment, conduits, cabling, etc. This project addresses needs identified in previous inspections. Under this contract, the consultant may also need to perform design work related to Sandy restoration work at the QMT facility. The Sandy restoration portion of the work contain FEMA funding and may be subject to relevant Federal regulation.
- Review available documentation and inspection reports related to the project scope and meet with Authority staff.
- Prepare final design documents for rehabilitation of selected alternative.
- Prepare construction specification and cost estimate.
- Assist the authority during bidding process and provide construction support services (CSS) during construction. CSS will be added to the contract at later date.
Duration of Contract 18 Months
RK-65A
CONSTRUCTION INSPECTION SERVICES FOR BRONX TOLL PLAZA AND INTERIM REPAIRS TO MANHATTAN TOLL PLAZA
$10M - $50M
Under this contract, the consultant will provide Construction Inspection Services for the Deck Replacement of the Bronx Toll Plaza construction contract and for Interim Repairs to Manhattan Toll Plaza.
- Inspect the construction work of the Contract, notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of the progress of the Contract. Review and monitor the Contractor's methods of protecting traffic, pedestrians and adjacent structures and ensure that the Contractor's Maintenance and Protection of Traffic is in place. Take immediate action on emergencies using sound engineering judgement.
- Ensure that all required permits have been obtained prior to the start of work. Make recommendations as to the capabilities of contractors, subcontractors and sources of materials and equipment proposed by them. Review contractor's schedule.
- Establish and implement procedures to be followed to expedite the processing of shop drawings, catalog cuts and submittals.
- Conduct progress meetings and special meetings as required. Assist in the resolution of disputes among the contractors.
- Make recommendations to the Engineer for such changes in the work as the Consultant may consider necessary or desirable. Provide an analysis of the validity and need for proposed change orders and assist the Authority in the subsequent negotiations.
- Provide lead abatement services which includes on-site inspections, air monitoring and sampling and testing.
Duration of Contract 63 Months
RK-65R
CONSTRUCTION INSPECTION SERVICES FOR RK-65R
$1M - $5M
Under this contract, the consultant will provide Construction Inspection Services for the reconstruction of the Manhattan Approach Ramps to the Manhattan Plaza to be performed at the RFK under RK-65R construction contract.
- Inspect the work of the Contract, notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of the progress of the Contract.
- Ensure that all required permits have been obtained prior to the start of work. Make recommendations as to the capabilities of contractors, subcontractors and sources of materials and equipment proposed by them.
- Establish and implement procedures to be followed for the expediting and processing of shop drawings, catalog cuts and submittals.
- Conduct progress meetings and special meetings as required. Assist in the resolution of disputes among the contractors.
- Make recommendations to the Engineer for such changes in the work as the Consultant may consider necessary or desirable. Provide an analysis of the validity and need for proposed change orders and assist the Authority in the subsequent negotiations.
- Assist the Engineer in the project close-out process.
Duration of Contract 18 Months
RK-76
DESIGN & CONSTRUCTION SUPPORT SERVICES FOR RK-76 (MISCELLANEOUS STRUCTURAL REHABILITATION AT RFK BRIDGE)
$1M - $5M
Under this contract, the consultant will provide design and construction support services during construction for the rehabilitation and repair of various bridge elements including subfloor-beams, floor-truss members, stringers, bearings, roadway joints, and other various structural elements requiring repair and rehabilitation. The designer will provide all the necessary design services required to prepare a complete bid package.
- Provide scope development services including analyzing and evaluating the results and findings from the most recent biennial inspection reports to confirm required repairs and provide various repair options. Develop repair details for Queens Suspension Span Stringer supports based on the findings of 'Queens Suspension Span Stringer Study'.
- Prepare design plans and specifications for the various bridge elements requiring rehabilitation and or replacement.
- Provide maintenance and protection of traffic (MPT) plans based on the various locations of required repairs.
- Prepare construction cost estimate and schedule.
- Assist the authority during bidding process and provide construction support services (CSS) during construction. CSS will be added to the contract at a later date.
Duration of Contract 36 Months
VN-35
CONSTRUCTION FOR VN-35 MISCELLANEOUS STRUCTURAL STEEL REPAIRS AND CONCRETE REHABILITATION
$10M - $50M
Under this contract, the contractor will perform miscellaneous steel repair and concrete rehabilitation work at various locations of the Verrazano Narrows Bridge facility.
- Miscellaneous structural steel repairs at various locations.
- Bearing Rehabilitation of the Belt Parkway Ramp.
- Concrete pier repairs of the Belt Parkway Ramp.
- Cleaning and painting the Brooklyn Approach Spans.
- Various flag repairs.
- Providing Maintenance and Protection of Traffic as required.
Duration of Contract 42 Months
VN-35
CONSTRUCTION INSPECTION SERVICES FOR VN-35 CONSTRUCTION CONTRACT
$1M - $5M
Under this contract, the consultant will provide Construction Inspection Services for the rehabilitation work to be performed at the VNB under VN-35 construction contract.
- Inspect the work of the Contract, notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of the progress of the Contract.
- Ensure that all required permits have been obtained prior to the start of work. Make recommendations as to the capabilities of contractors, subcontractors and sources of materials and equipment proposed by them.
- Establish and implement procedures to be followed for the expediting and processing of shop drawings, catalog cuts and submittals.
- Conduct progress meetings and special meetings as required. Assist in the resolution of disputes among the contractors.
- Make recommendations to the Engineer for such changes in the work as the Consultant may consider necessary or desirable. Provide an analysis of the validity and need for proposed change orders and assist the Authority in the subsequent negotiations.
- Assist the Engineer in the project close-out process.
Duration of Contract 50 Months
VN-87
DESIGN/ BUILD FOR REPLACEMENT OF KV SWITCHGEAR, UPGRADE OF THE POWER MONITORING SYSTEM AND INSTALLATION OF NEW 5KV STANDBY GENERATOR
$10M - $50M
The Contractor shall provide the necessary design and construction (Design/Build) services required to build a new 5KV Substation and demolish the existing 5KV switchgear in substation # 1 at the VNB Facility.
- Design and replace existing incoming switchgear including transformers, tie breakers, high voltage switches, etc.
- Design and construct building extension to the VNB service building auto garage to house the new substation.
- Design and construct new conduit to the bridge from the new substation location.
- Design and construct new generator for the VNB Facility.
- Demolish existing 5KV Switchgear equipment in Substation # 1.
- Prepare as-built drawings and O&M Manuals and provide as-needed MPT.
Duration of Contract 24 Months
BB-28
CONSTRUCTION INSPECTION SERVICES FOR BB-28
$10M - $50M
The consultant will provide Construction Inspection Services for the rehabilitation work to be performed at the BBT under BB-28 construction contract. Under this contract, the consultant will also need to inspect Sandy restoration work at the BBT facility. The Sandy restoration portion of the work contain FEMA funding and may be subject to relevant Federal regulation.
- Inspect the work of the Contract, notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of the progress of the Contract.
- Ensure that all required permits have been obtained prior to the start of work. Make recommendations as to the capabilities of contractors, subcontractors and sources of materials and equipment proposed by them. Review contractor's schedule.
- Establish and implement procedures to be followed for expediting and processing of shop drawings, catalog cuts and submittals.
- Conduct progress meetings and special meetings as required. Assist in the resolution of disputes among the contractors.
- Make recommendations to the Engineer for such changes in the work as the Consultant may consider necessary or desirable. Provide an analysis of the validity and need for proposed change orders and assist the Authority in the subsequent negotiations.
- Provide as-needed Pre-Construction Services and Assist the Engineer in the project close-out process.
Duration of Contract 48 Months
RK-65R
DESIGN / BUILD CONSTRUCTION OF THE TRAINING FACILITY AT RFK BRIDGE
$5M - $10M
The project is to provide design/build services for the construction of a one-story building. Contractor shall provide all necessary services to design and construct the project.Work includes construction of foundation, building, utility hook-ups, and all finishes necessary to provide a turnkey building ready for immediate occupancy.
- Design and build the foundation, building, utility and other associated work per the contract requirements.
- Secure all necessary permits from the applicable authorities.
- Submit the preliminary design and other milestone designs for authorities review and comments.
- Provide as needed MPT services.
- Submit as-built drawings and applicable O&M manuals.
Duration of Contract 12 Months
BB-21
CONSTRUCTION FOR BB-21 BBT SERVICE BUILDING ALTERATIONS
$1M - $5M
Under this contract, the contractor will rehabilitate the existing garage and office areas at the Brooklyn Battery Tunnel Service Building.
- Repurpose existing garage space to office space.
- Relocate existing workshops to more suitable locations.
- Provide direct access from the parking deck into the building.
- Improve ADA compliance.
- Eliminate existing trailers.
- Prepare As-Built documentation.
Duration of Contract 24 Months
RK-23A
CONSTRUCTION INSPECTION SERVICES FOR RK-23A
$1M - $5M
Under this contract, the consultant will provide Construction Inspection Services for the reconstruction of the Manhattan Approach Ramps to the Manhattan Plaza to be performed at the RFK under RK-23A construction contract.
- Inspect the work of the Contract, notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of the progress of the Contract.
- Ensure that all required permits have been obtained prior to the start of work. Make recommendations as to the capabilities of contractors, subcontractors and sources of materials and equipment proposed by them.
- Establish and implement procedures to be followed for the expediting and processing of shop drawings, catalog cuts and submittals.
- Conduct progress meetings and special meetings as required. Assist in the resolution of disputes among the contractors.
- Make recommendations to the Engineer for such changes in the work as the Consultant may consider necessary or desirable. Provide an analysis of the validity and need for proposed change orders and assist the Authority in the subsequent negotiations.
- Assist the Engineer in the project close-out process.
Duration of Contract 42 Months
HH-89
DESIGN AND CONSTRUCTION SUPPORT SERVICES FOR HH-89 CONSTRUCTION CONTRACT
$1M - $5M
The design consultant shall provide all the necessary design and design support services required to prepare a complete set of bid documents in order to rehabilitate all four Skewbacks and other substructures, (piers and abutments) at the HHB facility. The design will include rehabilitation work for skew backs, bent pedestals and the north and south abutments.
- Evaluate the scoping / investigation study of concrete cores for the skewbacks and other structures.
- Retrofit/Repair both North and South Skewback Anchor Blocks where the concrete is deteriorated.
- Retrofit/Repair for all Approach Concrete Piers for both Abutments.
- Develop appropriate construction staging/phasing schemes that has minimal impact on the facility daily operation and minimal long-term closures.
- Develop Construction Specifications and prepare construction cost estimate.
- Assist the authority during bidding process and provide construction support services (CSS) during construction. CSS will be added to the contract at a later date.
Duration of Contract 23 Months
VN-84
DESIGN AND CONSTRUCTION SUPPORT SERVICES FOR RECONSTRUCTION OF BELT PARKWAY RAMPS
$5M - $10M
Under this contract, the consultant will provide all the necessary design services required to prepare a complete set of bid documents for reconstruction of the upper level Staten Island and Brooklyn Upper Level elevated approach ramp decks and parapets at the VNB facility. The work also includes performing a coordination study and preliminary design for widening and replacement of the Belt Pkwy connector ramps to the Upper Level and Lower Level East Bound and widen and replace the Belt Parkway ramps, study the feasibility of a new ramp for Bus access to the Deayse Wharf area from the VNB and widening improvement to the East Bound Belt Parkway approach to the VNB.
- Review of previous feasibility study reports. Provide seismic evaluation and design for superstructure and substructure rehabilitation including bearings, cap beams, columns, joints and drainage.
- Design of deck and parapet replacement for all Upper Level approach decks and cellular structure ramps.
- Design of electrical and other utility (communications, new dry fire standpipe) related to above deck replacement work.
- Design of all MPT and necessary environmental work.
- All necessary coordination with TBTA and other agencies.
- Prepare construction cost estimates and provide construction support services (CSS) during construction. CSS will be added to the contract at a later date.
Duration of Contract 48 Months
L010063
DESIGN-BUILD FOR RECONFIGURATION OF JOHNSON AVENUE YARD
OVER $50M
Realignment and reconfiguration of Johnson Avenue Yard near Jamaica Station, Queens, in support of the Jamaica Capacity Improvements project.
- Replace and realign all 4 Johnson Avenue Yard tracks and a portion of the yard lead track.
- Install new electrically operated track switches.
- Construct a relieving platform under Track JY3 and a new retaining wall along the entire length of the yard.
- Install new perimeter yard lighting, CCTV surveillance system, and a yard Public Address [PA] system.
- Drainage and utility work [water supply].
- Waterproof select sections of Sutphin Blvd Bridge.
Duration of Contract 26 Months
L09382
HILLSIDE MAINTENANCE FACILITY ROOF REPLACEMENT
$1M - $5M
Remove the old roof on 2 Shops [Truck Shop and Wheel & Motor Shop Buildings] in the Hillside Maintenance Facility and replace with new PVC roof systems. The total roof replacement area is approximately 120,000 SF.
- Remove and dispose of old rubber roll roofing material.
- Repair existing roofing deck.
- Install new PVC roofing system.
Duration of Contract 15 Months
L09942 & L09955
ESCALATOR REPLACEMENT PROGRAM
$10M - $50M
- Repair or replace machine rooms.
- Install new CCTV cameras at top and bottom landings.
- Install new platform parapet walls.
- Make various concrete repairs.
- Install windscreen enclosures, signage, and bird prevention devices.
- Upgrade electrical, mechanical, and communication systems.
Duration of Contract 21 Months
L10033
DESIGN-BUILD 2ND MAIN LINE TRACK RONKONKOMA TO CENTRAL ISLIP
$10M - $50M
Design-Build for New 2nd Main Line Track between Ronkonkoma and Central Islip. This is the 1st phase of construction of a 2nd Mail Line Track from Ronkonkoma to Farmingdale. The Design-Build will include construction elements of the 2nd Main Line Track and associated infrastructure modifications as well as the fill and cut of the existing Right of Way to prepare the site for installation of trackwork.
- Civil site preparation.
- Earthwork, grading, drainage, and fill activities.
- Construct a retaining wall.
Duration of Contract 18 Months
L09253 & L09243
DESIGN-BUILD INFRASTRUCTURE IMPROVEMENTS AT COLONIAL ROAD
$10M - $50M
Design-Build for 3 infrastructure improvements at Colonial Road in Nassau County: A 12-car extension to an existing pocket track; replacement of Colonia Road Bridge; and improvements to Right of Way [ROW] and track drainage.
- Install new 12-car train pocket track including sound absorbing retaining wall and extensive landscaping.
- Replace Colonial Road Bridge with new concrete arch system to maintain existing roadway alignment.
- Improve [ROW] and track drainage deficiencies through installation of drainage ditches and retention ponds.
Duration of Contract 24 Months
L09121
DESIGN-BUILD WYANDANCH INTERMODAL FACILITY DEVELOPMENT
$10M - $50M
Design-Build Construction of a new Intermodal Facility [vertical parking garage] at LIRR Wyandanch Station. The work includes the Intermodal Parking Garage structure, a monumental tower, 3 elevators, 4 stairs, and associated site improvements. The new Parking Garage will complement the Town of Babylon's Transit Oriented Development [TOD] initiative by serving as a catalyst for creation of new public open spaces and plazas, redesigned roadway networks, and streetscape enhancements in the Station vicinity.
- Complete final design and provide materials, labor, and equipment.
- Construct new offices and equipment room spaces.
- Provide architectural finishes, doors, hardware, and accessories.
- Provide electrical and fire alarm systems, lighting, intrusion/security alarm/CCTV monitoring systems, communications, and HVAC.
- Plumbing and drainage.
- Fencing, signage, paving, striping, and site amenities.
Duration of Contract 18 Months
M09148
DESIGN/BUILD - PARK AVE VIADUCT DIRECT FIXATION
$1M - $5M
This Design/Build contract is for the investigation and design of the rehabilitation of the direct fixation system that supports the running rails for all four tracks atop the Park Avenue Viaduct from East 110th Street to East 131st Street. It will also perform as a pilot construction project to replace a number of the existing fasteners and fastener support pads in order to test the design resulting from the investigation. Work includes:
- Field inspection of the existing fasteners system.
- Investigation of probable causes for fastener and fastener pad failures.
- Recommendations of possible remediation that can be installed with minimal disruption of train operations.
- Installation of the proposed remediation.
Duration of Contract 12 Months
M10006
CONSTRUCTION - GCT LEAKS REMEDIATION
$10M - $50M
Phase II - This contract provides for leak remediation construction of various elements of Grand Central terminal infrastructure such as: the exterior stone work of the building's 42nd St. faςade and storefront windows: overhead roadway (viaduct) encircling the terminal including, Vanderbilt Avenue from 42nd St. to 45th St.(including taxi stand): North sidewalk and curb lane of 42nd St. along GCT: rehabilitation of two (2) bridges over 45th St. and installation of traffic light foundations on Vanderbilt Ave and 45th St. An agreement with NYCDOT has been executed which identifies NYCDOT's responsibility for the appropriate construction costs ranging from 0% - 100% for various elements.
- Repair and paint the stone fascia of Grand Central Terminal.
- Replace the waterproofing of the 42nd Street Viaduct and Vanderbilt Avenue sidewalk and roadway.
- Upgrade the Vanderbilt Avenue 42nd and 45th Street traffic light and pedestrian ramp components.
- Structural repairs of Vanderbilt Avenue roadway and sidewalk structural members.
- Repair and rehabilitate the 45th Street northbound and southbound NYCDOT bridges roadway and panels.
- Repair the Viaduct street lighting infrastructure.
Duration of Contract 35 Months
M10007
CONSTRUCTION MGMT./INSPECTION-GCT LEAKS REMEDIATION
$1M - $5M
Phase II - This contract provides construction supervision and inspection services for leak remediation to monitor a third party contractor during construction of various elements of Grand Central terminal infrastructure such as: the exterior stone work of the building's 42nd St. faςade and storefront windows: overhead roadway (viaduct) encircling the terminal including, Vanderbilt Avenue from 42nd St. to 45th St.(including taxi stand): North sidewalk and curb lane of 42nd St. along GCT: rehabilitation of two (2) bridges over 45th St. and installation of traffic light foundations on Vanderbilt Ave and 45th St.
- Provide resident engineer and office engineer to ensure construction complies with drawings and technical provisions.
- Chair bi-weekly construction meetings to review construction activities, schedule and budget.
- Issue technical directives to resolve field issues and provide monthly reports
- Review and approve as-built drawings.
Duration of Contract 35 Months
M08832
CONSTRUCTION - FORDHAM NORTHBOUND PLATFORM
$5M - $10M
The purpose of this project is to enhance pedestrian conditions and access to the northbound platform at Fordham Station. The scope of work consists of the following:
- Widen existing northbound platform using current Fordham University property
- Replace and widen the platform canopy decking on the northbound platform and replace signage and station amenities.
- Relocate canopy support structures away from the northbound platform edge
- Demolish and remove the existing northbound platform canopy
- Widen existing northbound platform by slab on grade using current Fordham University Property
- Replace and widen the platform canopy decking on the northbound platforms and install new tactile warning strips along platform edge.
Duration of Contract 22 Months
M09403
CONSTRUCTION DC TRACTION POWER SUBSTATION AT BREWSTER (B-52)
$5M - $10M
This contract provides for the construction of a new DC traction power substation on the Upper Harlem line at Brewster. The substation building will be prefabricated at the factory and installed on a preconstructed concrete pad.
- Construct prefabricated substation enclosure.
- Perform all site/civil work, (retaining walls, concrete vaults, pads)
- Set substation enclosure in place and make all internal connections.
- Complete all high voltage AC feeder work and DC third rail connections.
Duration of Contract 24 Months
M09424
PURCHASE MOBILE MOTOR ALTERNATOR SET
$500K - $1M
This contract will provide for the purchase of a trailer mounted mobile motor-alternator unit that can be transported as necessary to provide back-up signal power. The 150KVA synchronous motor alternator set and related equipment to convert a 480 volt, 60 Hz, 3 phase power source to a 480 Volt, 100 HZ, single phase power for Metro-North signal system. Purchase Shall Include:
- Fabrication of a trailer mounted motor-alternator set.
- Procurement of a Programmable Logic Controller (PLC) to control the motor-alternator startup and shut-down.
- Procurement of Supervisory Control and Data Acquisition (SCADA) system interface cabinet for monitoring and control.
- Procurement of all necessary high voltage step down transformers.
- Procurement of all necessary high voltage leads and cables.
Duration of Contract 6 Months
A36142
PROVIDE STATION IMPROVEMENTS- ADA ACCESSIBLE: 23RD STREET STATION
$10M - $50M
This project will provide vertical accessibility for 23rd Street Station on the Lexington Avenue Line in the borough of Manhattan. The station has been identified as an ADA Key Station and will meet all the guidelines set forth in the Americans with Disabilities Act Accessibility Guidelines. The work for this project will include:
- Installation of an accessible travel route
- Modifications of platforms to reduce gaps
- Modification of gates and agent booth windows
- Provide an elevator to each platform
- Installation of TTY's and public phones
- Provision of MVM's and AFAC units
- Installation of Braille signage throughout the station
Duration of Contract 25 Months
A36308, A36238, A36306, A36307, & A36239
STATION RENEWAL: 5 STATIONS
OVER $50M
This project work consists of 5 stations on the Liberty Line IND in the borough of Queens. This project will eliminate all deficient conditions at these stations. Work will include repair or replacement of mezzanine to platform stairs, mezzanine floors, doors and windows, interior and exterior walls, and canopies as required. The stations include: 111th Street, 104th Street, Rockaway Blvd, 88th Street and 80th Street. The scope of work includes the following tasks:
- Repair interior and exterior walls of mezzanine as required
- Provide new mezzanine to platform stairs
- Provide ADA compliant stainless steel handrails at new stairs
- Provide new guardrails and railings at each mezzanine passageway
- Provide ADA boarding area
- Provide new windows and doors as required
- Provide new platform windscreens
- Provide ADA tactile warning strips & rubbing board
- Provide cement, floor topping as required, paint entire station
Duration of Contract 27 Months
A37576
REMEDIATE WATER CONDITION
$1M - $5M
This project will remediate water condition problems at various stations located systemwide. Work on this project includes:
- Injecting grouting into active leaks through croncrete cracks, joints or holes located in roofs, ceilings, sidewalls, floors, etc.
Duration of Contract 24 Months
A80265
STATION CONSTRUCTION: ARTHUR KILL, STATEN ISLAND
$10M - $50M
This project will construct a new ADA-compliant passenger station and parking facility on the Staten Island Railway to replace the existing Atlantic and Nassau stations. Work on this project includes:
- The new construction of Arthur Kill Station along the Staten Island Railway. The major work items for the station will include foundation installation, ramp construction, platform construction, and overpass construction.
- The construction of new low-impact parking lot across Arthur Kill Road from the new station. The major work items for the station will include clearing the land, grading and paving, planting vegetation, and marking the pavement.
- The installation of a new traffic signal to allow pedestrians safe passage from the parking lot to the new station when crossing Arthur Kill Road.
- The demolition of Atlantic and Nassau Stations on the Staten Island Railway once the new station is complete and operable.
Duration of Contract 27 Months
C33086
HVAC SYSTEM UPGRADE - YUKON BUS DEPOT
$10M - $50M
This project will upgrade the HVAC systems at the Yukon Bus Depot in Staten Island. Work will include the replacement of existing oil fired HVAC and HV units with new gas fired HVAC and HV units and provide a new complete gas service to the depot. The major elements of this project shall include but not limited to the following:
- Remove and dispose of the existing HVAC and HV units where indicated
- Remove all oil systems, storage, tanks, and perform remediation of affected areas
- Install new gas fired HVAC and HV units as indicated
- Provide structural steel support to the HVAC and HV units and duct penetration areas
- Repair roof and flashing at all affected areas
- Install a new Gas Meter Room
Duration of Contract 18 Months
E31292
NEW VENTALATION PLANT: 46TH ST AND NORTHERN BLVD
OVER $50M
This project will construct a vent plant at 46th Street and Northern Boulevard on the Queens Boulevard Line. Vent plants are critical to safety, allowing evacuation of heat and smoke from tunnels in emergency conditions. The work includes a new vent plant structure, plenum,vent bays and flues, furnishing and installation of mechanical equipment, fans, dampers, and silencers, electrical service and distribution equipment, instrumentation & control, and communication equipment for operation of the fan plant locally as well as from a remote location. The construction of the new structure will also involve major site excavation and underground utilities work.
Duration of Contract 38 Months
S32760
REPLACE SOLID STATE SIGNAL EQUIPMENT: 8 LOCATIONS
$1M - $5M
This project will increase the reliability of the signal system by establishing a replacement program for solid state signal logic equipment that has reached the end of its useful life. This project will replace signal equipment at 8 locations. The locations include:
- Court Street - Broadway Line
- Whitehall Street - Broadway Line
- 125th Street - 8th Avenue Line
- 135th Street - 8th Avenue Line
- 145th Street - 8th Avenue Line
- Kings Highway - Brighton Line
- Coney Island Yard
- 21st Street - 63rd Street Line
Duration of Contract 20 Months
W32380
PASSENGER STATION LAN AT 31 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm. Room, passing around the station areas and back to the Comm. Room) with strategically-placed access nodes throughout (enclosures housing Ethenet switches for future IP connectivity) used specifically for local transport of all current and near future applications. This project will install Passenger Station LAN at 31 stations throughout the system.
Duration of Contract 17 Months
C33848
PROVIDE PERIMETER HARDENING: RCC, PCC & 130 LIVINGSTON PLAZA
$10M - $50M
This project will enhance the security of the Rail Control Center (RCC) located in the borough of Manhattan along with 130 Livingston Plaza in the borough of Brooklyn. The purpose of this project is to secure and protect these buildings. The scope of work includes the following tasks:
- Install bollards around the facilities;
- Enhance security at garage entrances and any lighting, CCTV alarms, or other equipment necessary for the control and monitoring of the security apparatuses;
- The design at the NYC Power Control Center (PCC) will require additional time and will be completed under a separate contract as per NYPD/NYCDOT request.
Duration of Contract 12 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PA/CIS cabinet at 87 Stations Systemwide. These are among the only remaining stations without any form of PA/CIS system. The system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network.
Duration of Contract 33 Months
B62006
BUS LANE ENFORCEMENT CAMERAS, PHASE 1
$1M - $5M
This project will equip approximately 90 buses with the Bus Lane Enforcement System (BLES). These buses will operate on the current SBS routes; M15 and BX12. The buses will be equipped with a video camera system designed to detect vehicles that violate traffic laws governing the use of bus lanes. The project will entail the design, installation, and implementation of equipment and software on selected buses that travel in bus lanes where camera enforcement is permitted. The system will provide evidence of the potential bus lane violations for review by enforcement staff. The enforcement staff will validate the violations and generate an evidence package that includes a Notice of Liability (NOL) and photographic images.
Duration of Contract 8 Months
C33845
STRUCTURE REPAIRS: DYRE AVENUE LINE
$5M - $10M
This project consists of the rehabilitation and repair of thruspans and open deck bridges along the Dyre Avenue Line. 1. East 180th Street a.Remove and rebuilt existing concrete pier at bent #24 b.Remove existing bearings and provide new neoprene bearings at bent #24 c.Clean and restore existing bearings and anchor bolt at bent #25 2. Kruger Avenue a.Repair concrete cracks and spalls at abutment and abutment cap, wing wall and wing wall cap, and back wall b.Remove and replace existing bearings c.Partially remove and rebuild back wall at north abutment 3. Bogart and Colden Avenue a.Remove unsound concrete and partially rebuild existing, deteriorated south abutment b.Remove and replace existing bearing at south abutment c.Repair concrete cracks and spalls at abutment and abutment cap, wing wall and wing wall cap, back walls, and pylons 4. Boston Post Road a.Repair concrete cracks and spalls at abutment and abutment cap, wing wall and wing wall cap, back wall, and concrete piers b.Partially remove and replace abutment cap and wing wall cap c.Remove and replace existing bearings d.Partially remove deteriorated and unsound concrete from existing piers and pier caps and restore e.Remove and rebuild portion of concrete arch at center pier 5. Secor Avenue a.Repair concrete cracks and spalls at abutment and abutment cap, wing wall and wing wall cap, and back walls b.Partially remove and rebuild back wall at south abutment c.Partially remove and replace existing abutment cap and wing wall cap d.Remove and replace existing bearings 6. Wickham Avenue and Ely Avenue a.Repair concrete cracks and spalls at abutment and abutment cap, wing wall and wing wall cap, and back walls
Duration of Contract 18 Months
C34821
ROOF REPLACEMENT AT 11 LOCATIONS, PHASE 3
$10M - $50M
This project is the third phase of an ongoing initiative to repair facility roofs; this iteration focuses on the replacement and repair at 11 locations in the Bronx, Brooklyn, Manhattan, and Queens:
- Marcy Avenue - Jamaica Line (CIR #127 at Williamsburg Bridge)
- Sutter Avenue/ Rutland Road - New Lots Avenue Line (CIR #351)
- Saratoga Avenue - New Lots Avenue Line (CIR #375)
- Rockaway Avenue - New Lots Avenue Line (CIR #395)
- New Lots Avenue - New Lots Avenue Line (Relay Room)
- Compressor Room: Queensboro Plaza
- Pelham Diesel Car Maintenance Shop
- 207th Street Administration Building
- 148th Street Yard (Relay Room)
- E 180th Street Yard - White Plains Road (Master Tower)
- Dyre Avenue Employee Facility (Dispatcher's Office)
The typical work includes the removal of the existing waterproofing, roofing, flashing, and all roofing materials to the deck and curbs then scraping, cleaning, patching, and preparing the existing roof deck for a new roof. This is followed by the installation of a new built-up white roofing system over coverboard and tapered insulation on the existing deck. Additional, miscellaneous repairs are also included in the scope at various locations: remove and replace metal fascia, remove and replace stone coping, remove and replace guardrails, remove and replace fencing, install pitch pockets, install flashing and counter flashing, remove and replace roof drains, repair of masonry structures, and remove and replace metal decks
Duration of Contract 18 Months
R34192
HEAVY SHOP EQUIPMENT REPLACEMENT
$10M - $50M
This project will purchase heavy shop equipment and machinery to replace equipment and machinery that have reached the end of their useful lives. Work will include:
- Purchase and installation of new parts washer tanks, truck washer, axle washer and bearing washer at the Coney Island Truck & Wheel Shop;
- Purchase and installation of a new AC and DC traction motor washer at the Coney Island Electric Motor Shop; and
- Purchase and installation of new wheel truing machines at 239th Street and Jamaica Maintenance Facilities.
Duration of Contract 36 Months
S32764
INTERLOCKING MODERNIZATION: 34TH ST
OVER $50M
This project will modernize and improve the reliability of 34th Street Interlocking. Work will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment. This project is necessary for the future implementation of Communications Based Train Control (CBTC). Work will include:
- Construction of new signal relay room; Master Tower, Reporting facility, Fire Suppression, HVAC Rooms, Replacement of all interlocking wayside signal equipment such as, but not limited to, stops, signs, switches and signal heads;
- Installation of a new messenger system and new cables as required for vital traffic circuits between interlockings;
- All signal power and signal power distribution necessary for the installation;
- Provisions for LED Starting Lights and Holding Lights;
- Provision for new platform CCTV.
Duration of Contract 50 Months
E34813
REPLACEMENT OF YARD LIGHTING
$10M - $50M
This project will replace yard lighting at the Jerome and Pelham railcar yards located in the Borough of the Bronx. Work will include:
- Replacement of the high mast, lighting towers, light fixtures to ensure operational safety
- Installation of new electrical distribution panels in existing Electrical Distribution Rooms
- Rodding of existing underground ducts for re-use and installation of new underground ducts
- Installation of new cable manholes
- Associated environmental work (asbestos abatement, contaminated water disposal)
Duration of Contract 24 Months
T80274
REHABILITATE ST. GEORGE INTERLOCKING, PHASE 1
$10M - $50M
This project is the first phase of the rehabilitation of the St. George yard and interlocking. Work for this multi-phased project is expected to include track and switch replacement, relocation of third rails, provision of rail lubrication system, signal modernization and drainage improvements. The scope of Phase 1 will include a portion of the identified work. The work proposed under this project is as follows: west end of the tunnel to the east end of the station platforms on Track 1, 2, 3, 4, 5 and North Shore Track NS2 up to signal SG30. The project consists of replacing all the tracks, ties, contact rail, and switches within the limits of the project. The VA dwarf signals will be refurbished and the incandescent bulbs replaced with light emitting diode assemblies.
Duration of Contract 20 Months
S32765
INTERLOCKING MODERNIZATION: WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking. Work will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment. This project is necessary for the future implementation of Communications Based Train Control (CBTC). Work will include:
- Construction of new signal relay rooms; Reporting facility, Fire Suppression, HVAC Rooms; Replacement of all interlocking wayside signal equipment such as, but not limited to, stops, signs, switches and signal heads; Replacement of all interlocking wayside signal equipment such as, but not limited to, stops, signs, switches and signal heads;
- Installation of a new messenger system and new cables as required for vital traffic circuits; between interlockings;
- All signal power and signal power distribution necessary for the installation;
- Provisions for LED Starting Lights and Holding Lights;
- Provision for new platform CCTV.
Duration of Contract 49 Months
CH057A
HAROLD STRUCTURES PART II - WEST BOUND BYPASS STRUCTURE
Over $100M
This Contract is for the construction of the Westbound bypass structure within Harold Interlocking for the East Side Access Project. The work shall include but is not limited to:
- Construct underground by-pass tunnel, approach structures for new tunnels and the extension of existing bridges and underpass structures.
- Support of Excavation
- Excavation and backfill
- Construct concrete structure
- Construction catenary foundations and poles
- Install direct fixation track
- Install ballasted track and switches
Duration of Contract 30 Months
CS284
SYSTEMS PACKAGE PART II - TRACTION POWER, TRACK AND SIGNALS
Over $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project. The work shall include, but is not limited to, the following:
- Installation of track (furnished by owner), special work, switch machines, third rail, finish track and invert slabs, drainage and embedded conduits and tunnel corrosion control system.
- Fabricate, install, test and commission all traction power substations and wayside equipment to support the traction power system in the ESA Tunnels and GCT.
- Install, test and commission the signaling system from the GCT Tail Tracks to Harold interlocking
Duration of Contract 48 Months
CH057
HAROLD STRUCTURES PART II - LOOP BOX STRUCTURE, 48TH ST. BRIDGE, D APPROACH STRUCTURE
$50M -$100M
This Contract shall be responsible for earth and site work, utility relocations, track realignment, drainage, and construction of new heavy civil structures within the LIRR Harold Interlock located in Queens. The scope of work shall include but is not limited to:
- Construct retaining walls, catenary and utility & catenary tower foundations and poles, access roads
- Install direct fixation track, traction power, lighting, stand pipe and fire protection systems.
- Installatiion of monitoring devices for existing structures and ground conditions
- Perform all required incidental abatement (ballast, soils, asbestos, lead paint).
Duration of Contract 30 Months
PS838
ON-CALL DESIGN AND ENGINEERIN CONSULTANT SERVICES
$1M - $5M
Several base on-call contracts for design and engineering consultant services will be awarded through this solicitation. Under this arrangement, "Task Orders" against the base contracts will be issued for the specific consulting services as MTACC's needs are identified. These Task Orders will include detailed specifications which can include the following:
- Archtectural, Interior, Landscape design
- Electrical, Structural, Civil and Mechanical Engineering
- Construction Inspection and Management
Duration of Contract 36 Months
CM014B
CONSTRUCTION OF GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
This Contract is for the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility which includes foundation, underground utilities, CMU walls, structural steel framing, mechanical, electrical, plumbing, fire protection, and architectural finishes. Under this Contract, the Contractor shall also fit-out of 44th Street and 50th Street Ventilation Facilities. The scope of work includes, but is not limited to:
- Construction of new LIRR GCT Concourse.
- Intermodal Connections and Interfaces with MNR's GCT including dining concourse, 45th street cross passageway, 47th street cross passageway.
- Installation of elevators and escalators using the designated Contract VM014 contractor.
- Perform the local station testing of GCT concourse and caverns.
Duration of Contract 32 Months