mta.info

Forecast of NYCT, MNR, LIRR, B&T, CC, BUSCO and SIR Contracts
to be Advertised and Proposals to be Solicited

New York City Transit
Long Island Rail Road
Metro-North Railroad
Bridges and Tunnels
Capital Construction
MTA Bus Company
Staten Island Railway


Capital Construction
Brief Description of Work
JUL 2009

VM014*
INSTALL VERTICAL CIRCULATION ELEMENTS (MTACC)
EAST SIDE ACCESS - MANHATTAN
$50M - $100M

This project is to fabricate and install 15 elevators and 44 escalators within Grand Central Terminal for the East Side Access Project. The work will be coordinated with the design for the structural, architectural, mechanical and electrical elements in the caverns for the new LIRR Terminal.

Duration of Contract 48 Months


CM013*
CONSTRUCT 50TH ST. VENTILATION FACILITY (MTACC)
EAST SIDE ACCESS - MANHATTAN
$50M - $100M

This project is for the demolition of existing buildings, excavation support of the street, installation of decking over the street, relocation of utilities, excavation of soil and rock. and construction of the ventilation structure shell for the facility at 50th Street in Manhattan. The scope of work includes following tasks.

Duration of Contract 24 Months



Capital Construction
Brief Description of Work
AUG 2009

CM012*
CONSTRUCT MANHATTAN STRUCTURES PART II (MTACC)
EAST SIDE ACCESS - MANHATTAN
Over $100M

This project is to construct the structural, architectural, mechanical and electrical elements of the east and west caverns for the new Long Island Rail Road Terminal within Grand Central Terminal. The scope of work includes the following tasks.

Duration of Contract 40 Months



Capital Construction
Brief Description of Work
SEPT 2009

A36126*
REHABILITATE CORBIN BUILDING (MTACC)
FULTON STREET TRANSIT CENTER - MANHATTAN
$10M - $50M

This project is to restore the Corbin Building, a historic structure adjacent to the Transit Center in Lower Manhattan. The scope of work includes the following tasks.

Duration of Contract 24 Months



Capital Construction
Brief Description of Work
OCT 2009

A-36138*
COMPLETE R/W STATION & UNDERPASS DEY STREET CONCOURSE (MTACC)
FULTON STREET TRANSIT CENTER - MANHATTAN
$10M - $50M

This project is to complete the finishes and systems for the structures required for the Dey Street Concourse and underpasses below the R/W Cortlandt Street Station. The scope of work includes the following tasks.

Duration of Contract 24 Months



Capital Construction
Brief Description of Work
DEC 2009

C-26007*
CONSTRUCT 72ND ST STATION CAVERN & TUNNELS (MTACC)
SECOND AVENUE SUBWAY - MANHATTAN
Over $100M

This project is to construct the 72nd Street Station cavern and tunnels to the existing 63rd Street/Lexington Avenue Station. The scope of work includes the following tasks.

Duration of Contract 41 Months


C26014*
DEMOLISH BUILDING & RELOCATE UTILITIES FOR 72ND ST. STATION (MTACC)
SECOND AVENUE SUBWAY - MANHATTAN
$10M - $50M

The project is to demolish the existing buildings, relocate utilities and clear the sites for the 72nd Street Station on the new 2nd Avenue Subway Line. The scope of work includes the following tasks.

Duration of Contract 12 Months



Long Island Rail Road
Brief Description of Work
JUL 2009

N00654
REHABILITATE BUILDING (LIRR)
BRENTWOOD STATION
$100K - $250K

This project is to fabricate and install storefront type windows and doors in the Brentwood station building.

Duration of Contract 2 Months


N00643
REHABILITATE BUILDING (LIRR)
CENTRAL ISLIP STATION
$100K - $250K

This project is to fabricate and install storefront type windows and doors in the Central Island station building.

Duration of Contract 2 Months


L08203*
REPLACE ESCALATORS (LIRR)
MERRICK, BELLMORE & MASSAPEQUA PARK STATIONS
$1M - $5M

This project is to replace three escalators, one each at Merrick, Bellmore and Massapequa Park stations. The project scope of work includes the following tasks.

Duration of Contract 27 Months


L08240 and L08926
IMPROVE RADIO COVERAGE/INFRASTRUCTURE (LIRR)
VARIOUS LOCATIONS
$1M - $5M

This project is to install monopole radio towers in three to five locations in Nassau and Suffolk counties. The 25-compliant digital radio will have ancillary systems (power filtering/backup, surge suppression, grounding, etc.). The project scope of work includes the following tasks

Duration of Contract 12 Months



Bridges and Tunnels
Brief Description of Work
JUL 2009

VN-03 II(cm)
PROVIDE INSPECTION SERVICES FOR TOLL PLAZA IMPROVEMENTS PHASE A (BT)
VERRAZANO NARROWS BRIDGE - STATEN ISLAND
$250K - $500K

This project is to provide inspection services for the project to rehabilitate the eastbound Staten Island approach to the Verrazano Narrows Bridge Toll plaza. The scope of work includes the following: structure demolition, excavation and disposal, cast in place concrete, pavement and drainage reconstruction, roadway repairs, pavement markings, survey, pedestrian tunnel modification, electrical removals, maintenance and protection of traffic. The inspection services provided by the consultant will be performed under the general direction of the Triborough Bridge and Tunnel Authority and will include the following duties and responsibilities.

Duration of Contract 14 Months


TN-87B/TNM-338(cm)
PROVIDE INSPECTION SERVICES FOR THE ANCHORAGE & TOWER BASE PROTECTION REHABILITATION (BT)
THROGS NECK BRIDGE - QUEENS
$250K - $500K

This project is to provide inspection services for the rehabilitation of the Bronx and Queens anchorage and tower base protection systems at the Throgs Neck Bridge. In addition, the Bronx Anchorage fender will be modified to provide mooring facilities for NYFD fireboats and the Queens Anchorage fender to will be rehabilitated to remove and replace damaged timber pile dolphins with new dolphins. The services provided by the consultant will be performed under the general direction of the Triborough Bridge and Tunnel Authority and will include will include the following duties and responsibilities.

Duration of Contract 27 Months


VN-03 II
CONSTRUCT TOLL PLAZA IMPROVEMENTS PHASE A (BT)
VERRAZANO NARROWS BRIDGE
$1M - $5M

This project is to rehabilitate the eastbound Staten Island approach to the Verrazano Narrows Bridge Toll plaza.The scope of work includes the following elements: structure demolition, excavation and disposal, cast in place concrete, pavement and drainage reconstruction, roadway repairs, pavement markings, surveys, pedestrian tunnel modification, electrical removals, and maintenance and protection of traffic.

Duration of Contract 12 Months


BW-97/97A(cm)
PROVIDE INSPECTION SERVICES FOR ANCHORAGE CONCRETE REPAIRS & REHABILITATION OF EYEBAR CHAMBERS (BT)
BRONX WHITESTONE BRIDGE
$1M - $5M

This project is to provide inspection services for the anchorage concrete repairs and rehabilitation of eyebar chambers on the Bronx Whitestone Bridge. The services provided by the consultant will be performed under the general direction of the Triborough Bridge and Tunnel Authority and will include will include the following duties and responsibilities.

Duration of Contract 40 Months


TN-87B/TNM-338
REHABILITATE ANCHORAGE & TOWER BASE PROTECTION (BT)
THROGS NECK BRIDGE
$1M - $5M

This project is to rehabilitate the Bronx and Queens anchorage and tower base protection systems at the Throgs Neck Bridge. In addition, the Bronx anchorage fender will be modified to provide mooring facilities for NYFD fireboats, and the Queens anchorage fender will be rehabilitated to remove and replace damaged timber pile dolphins with new dolphins. The scope of work includes the following tasks.

Duration of Contract 24 Months



Bridges and Tunnels
Brief Description of Work
AUG 2009

BW-97/97A
REPAIR ANCHORAGE CONCRETE & REHABILITATE EYEBAR CHAMBERS (BT)
BRONX WHITESTONE BRIDGE - QUEENS
$5M - $10M

This project is to repair the anchorage concrete and rehabilitate the eyebar chambers on the Bronx Whitestone Bridge in Queens. The scope of work includes the following tasks.

Duration of Contract 36 Months



New York City Transit
Brief Description of Work
JUL 2009

A36065
REPAIR DYCKMAN ST. STATION COMPONENTS (NYCT)
BROADWAY LINE - MANHATTAN
$10M - $50M

This project is to reconstruct station platforms, canopies, railings, and miscellaneous items at the end platform level at the Dyckman Street Station on the Broadway/7th Avenue Line. In addition, the span work will include the removal of track and third rail. The breakout of duct banks will provide new modified Type 2 track with drainage. The scope of work also provides for façade repair and stair rehabilitation. This project will be constructed in conjunction with the replacement of canopies at five stations on the Broadway Line (C33126).

Duration of Contract 31 Months


C33126
REPLACE CANOPIES AT FIVE STATIONS (NYCT)
BROADWAY LINE - MANHATTAN & BRONX
$10M - $50M

This project is to repair and/or replace roof canopies at five stations on the Broadway Line in Manhattan and the Bronx: 207th Street, 215th Street, 225th Street, 238th Street, and 242nd Street. Canopy work will be performed at platforms and control houses. This project will be constructed in conjunction with the project to replace platforms at the Dyckman Street Station on the Broadway 7th Avenue Linet (A36065).

Duration of Contract 31 Months


C34770*
REPAINT PORTAL TO 41ST AVE (NYCT)
ASTORIA LINE BMT QUEENS
$10M - $50M

This project is for the comprehensive removal of the lead based paint on portions of the steel structure of the Astoria and Flushing Lines near Queensboro Plaza. The structure will be painted with a new three-coat, more durable painting system. The scope of work will include surface preparation/stripping and structural steel painting (re-coating) of steel sections.

Duration of Contract 18 Months


C52093
FURNISH/INSTALL ACCESS CONTROL & INTRUSION DETECTION SYSTEM (NYCT)
270 LOCATIONS
$10M - $50M

This project is to furnish and install an access and intrusion control system with related auxiliary equipment at approximately 270 passenger station communication rooms. The communications rooms are located in underground and elevated stations throughout the boroughs of Manhattan, Brooklyn, the Bronx and Queens. The system will include proximity card readers and magnetic door locks. These systems will provide a local alarm indication, as well as central monitoring at a remote site.

Duration of Contract 24 Months


B40641
PURCHASE 135 COMPRESSED NATURAL GAS BUSES (NYCT)
OVER $50M

This project is to purchase 135 40-foot low floor buses powered by compressed natural gas (CNG) - 90 for NYC Transit Department of Buses and 45 for the MTA Bus Company - with an option to purchase up to 375 additional buses - 195 for NYC Transit Department of Buses and 180 for the MTA Bus Company. Bus specifications include, but not limited to the following: electronic destination signs, hard insert passenger seating, two doors, air brakes, custom supplied tires (six), basic white paint with NYCT decaling, and multiplex electrical system.

Duration of Contract 10 Months


C40455
RECONSTRUCT CLARA HALE DEPOT (NYCT)
MANHATTAN
OVER $50M

This design/build project will replace the present Clara Hale Depot at 721 Lenox Avenue, Manhattan with a new depot. The new depot will be a state of the art facility and provide indoor storage for approximately 150 standard buses. The scope of work includes the following tasks.

Duration of Contract 36 Months



New York City Transit
Brief Description of Work
AUG 2009

C80269
REPLACE FLOOR (NYCT)
ST. GEORGE TERMINAL - SIR
$1M - $5M

This project is to repair and replace part of the structural floor slab and all the floor finish at the St. George Terminal Station, an inter-modal facility at the north end of the Staten Island Railway where connections to the Staten Island ferry are available. All floor surfaces on the railroad concourse, between bottom of stairs to track platform entrances from track 1 through 12 which are accessible to the public, will be restored or replaced. This project will also include the provision of a new station room with heating and cooling.

Duration of Contract 11 Months


A36116
CONSTRUCT PLATFORM ACCESSIBILITY IMPROVEMENTS (NYCT)
45TH ROAD HOUSE SQUARE
$5M - $10M

This project is to construct accessibility (ADA) improvements at the platform level at 45th Road Court House Square Station on the Flushing Line in Queens. The scope of work includes installing ADA platform edge, boarding area and signage and handrails; rebuilding part of the platform slab; and replacing the full platform.

Duration of Contract 14 Months


C34785
REPAIR & REPLACE ROOFS (NYCT)
VARIOUS LOCATIONS
$5M - $10M

This project is to repair and replace NYC Transit building roofs at the following locations: Concourse Yard Tower, Corona Yard Compressor Room, 207th Street Yard Master Tower "A", 240th Street Yard Master Tower, 38th Street Yard Master Tower, Woodlawn Station Relay Room, Jerome Yard Maintenance Facility, Canarsie Yard Car Wash, and the Metropolitan Avenue female locker room. The roof replacement will include the following tasks.

Duration of Contract 24 Months


W32697
FURNISH & INSTALL PUBLIC ADDRESS CUSTOMER INFORMATION SYSTEM CABINETS (NYCT)
44 LOCATIONS
$5M - $10M

This project is to furnish and install public address cabinets at 44 stations. Enhanced public address systems will provide audible information, and customer information screens (CIS) will provide information in a visual format at the following 44 stations.

Duration of Contract 18 Months


C34795
PAINT ELEVATED STRUCTURE (NYCT)
BROADWAY LINE - MANHATTAN
$10M - $50M

This project is to provide overcoat paint on the 125th Street Arch between LaSalle and 133rd Streets on Broadway 7th Avenue Line in Manhattan. The scope of work includes the following tasks.

Duration of Contract 18 Months


W32686
UPGRADE VHF RADIO SYSTEM - PHASE I (NYCT)
VARIOUS LOCATIONS
OVER $50M

This project will consolidate, replace and upgrade the radio frequency infrastructure of the existing Rapid Transit Operation (RTO) at locations throughout the Bronx, Brooklyn, Manhattan and Queens. The first phase of the project will be to purchase all equipment for the A and B Divisions and complete the upgrade for the A Division only. The main objective of this project is to meet the FCC mandate of moving all VHF analog radios from Wide Band radio transmission to Narrow Bank radio transmission. The expectation is to transition the existing radios from wide to narrow band in a seamless way to minimize disruption of NYC Transit train services. The project will further provide a head end at the NYC Transit Rail Control Center with a backup at Livingston Plaza as well as enhancements such as GPS, alarm monitoring and controls and network connectivity. There will be remote management capabilities, uninterrupted power supply service during power failures, and it will be configurable for redundant patch network that will make use of the SONET/ATM infrastructure. The scope includes communications, electrical, environmental, mechanical and architectural requirements.

Duration of Contract 35 Months



New York City Transit
Brief Description of Work
SEPT 2009

C40458
INSTALL STORM WATER SEWER - CHARLESTON ANNEX (NYCT)
ARTHUR KILL ROAD & ALLENTOWN LANE - STATEN ISLAND
$5M - $10M

This project is to install a storm water sewer under Arthur Kill Road and Allentown Lane on Staten Island with an outfall into the Arthur Kill Bay, as required by New York City Department of Environmental Protection. A storm sewer is necessary to legally remove storm water from the soon-to-be-constructed Charleston Bus Annex in Staten Island which will meet bus storeage for 220 MCI buses.

Duration of Contract 13 Months


A80265*
CONSTRUCT NEW STATION & PARKING LOT - ARTHUR KILL ROAD (NYCT)
STATEN ISLAND RAILWAY
$10M - $50M

This project is to construct a new Arthur Kill Station along the right of way between the Nassau and Atlantic Stations on Staten Island. The project also requires the construction of a 150 car parking lot across the street from the new station. The scope of work includes the following elements.

Duration of Contract 25 Months



New York City Transit
Brief Description of Work
OCT 2009

A36078
CONSTRUCT GUN HILL ROAD INTERMODAL FACILITY (NYCT)
WHITE PLAINS ROAD LINE - BRONX
$1M - $5M

This project is to construct a coordinated Bus Intermodal Facility adjacent to the Gun Hill Road Station on the White Plains Road Line in the Bronx. Major elements of work include: reconfiguration of White Plains Road north of Gun Hill Road; creation of bus stops, bus layover and bus turn around lanes; and construction of a transit plaza adjacent to the station. In addition, the NYC Williamsbridge Park south of Gun Hill Road will be rehabilitated, and minor repairs to the park building will be completed.

Duration of Contract 9 Months



New York City Transit
Brief Description of Work
NOV 2009

C31361
TEST CONCRETE CYLINDERS (NYCT)
VARIOUS LOCATIONS
$250K - $500K

This project is to physically test concrete samples taken from various NYC Transit construction sites in order to insure the quality of the materials used. The contractor will acquire samples from the work sites, provide physical testing of the samples and submit written reports detailing the results of the tests. The contractor will follow the standards for sampling and testing provided by the American Society for Testing and Materials and the New York City Building Code.

Duration of Contract 36 Months


C34597
INSPECT CONCRETE (NYCT)
VARIOUS LOCATIONS
$500K - $1M

This project is for the services of qualified inspectors to check mixes, materials and equipment at concrete batch plants. The inspectors will also ship the ready-mixed concrete, ballast and asphalt from plants to various job sites in New York City and submit all related documents to the NYC Transit Engineering Services Division.

Duration of Contract 36 Months


C40456
INSTALL NEW BOILER (NYCT)
AMSTERDAM DEPOT
$1M - $5M

This project is to remove two boilers and associated equipment and install one new boiler and associated equipment. A new gas meter room and gas distribution system will also be installed.

Duration of Contract 9 Months



New York City Transit
Brief Description of Work
DEC 2009

A36158
REPAIR BRICK ARCH CEILING (NYCT)
181ST ST. STATION
$1M - $5M

This project is to repair the brick arch at the 181st Street Station on the Broadway/ 7th Avenue Line. The arch must be restored with materials that match the original. The project elements include the brick arch, mosaics and architectural ornamentation. The work will be coordinated with general orders available for other NYC Transit projects.

Duration of Contract 12 Months



Metro-North Railroad
Brief Description of Work
JUL 2009

M07806
CONSTRUCT POWER IMPROVEMENTS (MNR)
HARLEM & HUDSON LINES
$10M - $50M

The project is to construct up to four new traction power substations at the following locations: Valhalla, Croton Falls, Goldens Bridge and Katonah.The new substations will utilize a prefabricated structure that can be pre-assembled and factory tested, transported to the site and installed on pre-constructed concrete pads. An option to construct additional substations will also be included.

Duration of Contract 30 Months



Metro-North Railroad
Brief Description of Work
AUG 2009

M07799*
CONSTRUCT DRAINAGE & UNDERCUTTING IMPROVEMENTS (MNR)
HARLEM LINE
$5M - $10M

This project is to construct drainage improvements from Mott Haven to Fordham on the Harlem Line. Work will include the installation of lateral and longitudinal drainage lines and connections to NYCDEP sewers. Track outages will be required for the drainage installation, and availability/scheduling will be finalized prior to start of construction.

Duration of Contract 18 Months



Metro-North Railroad
Brief Description of Work
DEC 2009

M07735
CONSTRUCT NORTH BARRY AVENUE OVERHEAD BRIDGE (MNR)
MAMARONECK NY
$1M - $5M

This project is to replace the superstructure and rehabilitate the substructure on the North Barry Avenue Bridge in Mamaroneck, NY on the Metro-North Railroad New Haven Line.The bridge will be closed during construction. The scope of work includes a steel multi-girder superstructure and a concrete deck for the westerly pedestrian and utilities structure. A steel through-girder with floor beams encased in concrete superstructure will be constructed for the vehicular and the easterly pedestrian structure. The top portions of the existing abutments will be modified to accommodate the new superstructure. The bridge approach work will include paving, sidewalks and utility work. The installation and removal of two temporary catenary towers is also included in the contract.

Duration of Contract 18 Months


M07366*
INSTALL CABLE (MNR)
SIGNAL SYSTEM REPLACEMENT
$5M - $10M

This project is to install and test aerial duct, messenger suspension strand, fiber optic and copper cables and related hardware, and signal power transformers. The out-of-service cables and hardware will be removed. The work is to be performed on a contiguous section of railroad comprised of a short section of Metro-North's Harlem Line and on the New Haven Line from Woodlawn, NY to Riverside, CT including the bridge crossing the Minus River at Cos Cob, CT. The work area is an approximately 18.6 miles four track mainline territory which is entirely electrified, utilizing 700 Volt DC third rail between CP112 at Woodlawn and Pelham, NY and 13,000 Volt 60 Hertz AC overhead catenary for the remainder.

Duration of Contract 18 Months



MTA Bus Company
Brief Description of Work
OCT 2009

C40464*
REPLACE ROOF & VENTILATION SYSTEM (BUSCO)
EASTCHESTER DEPOT - BRONX
$1M - $5M

This project is to replace a roof and install a new ventilation system at Eastchester Depot maintenance building that is approximately 34,000 square feet. The scope of work includes the following tasks.

Duration of Contract 43 Months


C33084*
UPGRADE PARKING LOT (BUSCO)
JFK/BAISLEY BUS DEPOTS
$10M - $50M

This project at JFK is to provide 68,400 square feet of parking area for buses, service vehicles and employee parking area with capacity for 22 articulated buses and 64 vehicles. The Baisley Park parking area of approximately 3.2 acres, has a drainage problem so that the area becomes impassable. The scope of work includes the following tasks.

Duration of Contract 42 Months


 

* Funded by Federal Grant