April 4th 2012 To May 25th 2012
LOCATION: | DESCRIPTION OF WORK 1 |
100th to 99th Streets |
Rebar cage fabrication for slurry walls and material storage. |
99th to 97th Streets |
Preparing for guide wall installation & Secant Piles. |
97th to 96th Streets |
Preparation for Slurry wall operations on the East side of 2nd Avenue from 95th Street to 98th Street. |
96th to 95th Streets |
Switch to south closure. Slurry wall operations. |
94th Street East of 2nd Avenue |
Slurry Wall operations. |
94th Street South West corner |
Utility work at entrance 1 (former Rainbow Hardware). Secant Pile Installation. |
93rd Street between 1st and 2nd Avenues |
N.E corner 93rd St. Intermittent closures of 93rd St for utility relocations & secant pile installation. |
93rd to 92nd Street |
Removal of site equipment. |
92nd to 91st Streets |
Installing tunnel liner and concreting. |
88th to 87th Streets |
Installation of employee trailers and offices. |
87th to 86th Streets |
Delivery and installation of structural steel for North Muck Enclosure. Construction of North Muck Enclosure. |
86th Street Between 1st and 3rd Avenue |
Demobilization of center work zone. Mobilization of work zone on the South side of 86th Street for utility relocations. Reducing sidewalk on South side of 86th Street to 7 feet. Traffic will be moved to North side of 86th Street between 1st and 2nd Avenues. |
86th Street North West corner Ancillary 2 |
Interior demolition work in preparation for excavation. Installation of support of excavation. Con Edison cable installation. |
86th to 85th Streets |
Maintenance and Protection of Traffic. Contractor material storage area. |
85th to 84th Streets |
Maintenance and Protection of Traffic. Contractor material storage area. |
84th to 83rd Streets |
Delivery and installation of structural steel for South Muck Enclosure. Construction of South Muck Enclosure. Installation of new sewer and water lines at 1602 Second Avenue Entrance 1 (former Tony's DiNapoli). Contractor expects to begin controlled blasting activities 2nd week in April. |
83rd Street North West corner (Ancillary 1) |
Excavation and installation of support of excavation in preparation for the installation of decking. |
83rd to 82nd Streets |
Preparation of area for dewatering equipment. |
79th to 78th Streets |
Concrete deliveries to tunnel utilizing center work zone. Intermittent controlled blasting in tunnel. |
74th to 73rd Streets |
Operation of water treatment plant |
73rd to 72nd Streets |
Controlled blasting activities. Shotcrete operations in cavern. |
72nd Street North West corner Ancillary 2 |
Contractor expects to begin controlled blasting activities 1st week of April. |
72nd to 71st Streets |
Contractor material storage and maintenance area. |
72nd Street South East corner Entrance 3 |
Continuing building demolition. |
71st to 70th Streets |
Contractor offices and storage area. |
70th to 69th Street |
Controlled blasting activities. Shotcrete operations in cavern. |
69th Street North West Side Ancillary 1 |
Installation of deck beams and decking. Contractor expects to mobilize crane on site 3rd week of April. Controlled blasting is scheduled to begin 1st week of May. |
69th Street East Side |
Shotcrete operations in underground cavern. |
67th to 66th Street West Side |
Concrete delivery operations to underground cavern. |
63rd Street North West corner |
Hoisting of materials through excavation in Plaza. |
63rd Street between 3rd Avenue and Lexington Avenues |
Intermittent access to existing station below 63rd St. |
3rd Avenue between 63rd and 64th Street |
Hoisting of material through excavation in Plaza. Occupation of parking lane on West Side of 3rd Avenue. |
63rd Street between 3rd Avenue and Lexington Avenue |
Intermittent access to existing station below 63rd Street. |
64th Street and 3rd Avenue |
Installing employee changing trailers on North East corner of 64th Street and 3rd Avenue. |
WORK HOURS:
MONDAY - FRIDAY, 7:00 AM TO 10:00 PM
SATURDAY, 10:00 AM TO 7:00 PM
WORK UNDER DECKING PERMITTED 24 HOURS
BE ADVISED: Con Ed, Empire City Subway and Verizon may be performing cable and gas line work outside regular SAS construction Hours. If you have additional questions, please contact Claudia Wilson at (212) 792-9716 from 9:00AM to 5:00PM Monday through Friday, or contact the 2nd Avenue Subway Hotline 24 hours/7 days a week at (646)252-2670.
TRAFFIC UPDATES
100th to 95th Streets
- Four lanes of traffic on the West side of Second Avenue
- Work zone will be set up on the East side of Second Avenue
- The East side work zone will be approximately 40 Feet wide, plus 7 foot sidewalk
- No Standing on the West side of Second Avenue 95th street to 100th Street
95th Street to 91st Streets
- Four lanes of traffic currently on West Side of 2nd Avenue
- Work zone is set up on the East Side of 2nd Avenue
- The East Side work zone will be approximately 40 Feet wide, plus 7 foot sidewalk
- No Standing Anytime on the West Side of Second Avenue
- Truck loading and unloading West side of Second Avenue 93rd to 91st Streets
- Parking permitted on West Side 7PM-7AM Weekdays and all day Saturday
87th to 82nd Streets
- From 88th Street to 82nd Street. Four lanes of traffic West Side of 2nd Avenue
- No Standing Anytime on the West Side of Second Avenue 88th Street to 87thStreet
- No Standing Anytime on the West Side Second Avenue except for loading and unloading between 85th and 82nd Streets
74th to 66th Streets
- Work zone is set up on the East Side of Second Ave
- The East Side work zone will be approximately 40 feet wide, plus 7 foot sidewalk
- No Standing at Anytime on the West Side of Second Avenue between 66th and 67th Street, 69th and 70th, and 72nd and 73rd Streets
- No Standing on West Side except trucks loading and unloading 10AM to 4PM between 70th and 72nd and 73rd to 74th Streets
- No Standing Anytime on the East side of Second Avenue between 74th and 75th Street. Truck layover zone.
- Parking ALLOWED on West Side 7PM-7AM Weekdays and all day Saturday & Sunday
63rd Street
- No Standing Anytime on 63rd St between 2nd and 3rd Avenues, except for School Bus Loading Zone in front of 213 E. 63rd St.
- No Standing Anytime on 63rd St between 3rd Avenue and Lexington Avenue. Two lanes of traffic maintained, with sporadic temporary closures to one lane.
- No Standing Anytime on 63rd St for about 180 feet West of Lexington Avenue. Two lanes of traffic maintained.
If you have additional questions, please visit the Keeping in Touch page for contact information.