SAS Newsletters Latest Newsletter updates

April 4th 2012 To May 25th  2012

LOCATION:

DESCRIPTION OF WORK 1

100th to 99th Streets

Rebar cage fabrication for slurry walls and material storage.

99th to 97th  Streets  

Preparing for guide wall installation & Secant Piles.

97th to 96th Streets

Preparation for Slurry wall operations on the East side of 2nd Avenue from 95th Street to 98th Street.

96th to 95th Streets

Switch to south closure. Slurry wall operations.

94th Street East of 2nd Avenue

Slurry Wall operations.

94th Street South West corner

Utility work at entrance 1 (former Rainbow Hardware). Secant Pile Installation.

93rd Street between 1st and 2nd Avenues

N.E corner 93rd St. Intermittent closures of 93rd St for utility relocations & secant pile installation.

93rd to 92nd Street  

Removal of site equipment.

92nd to 91st Streets

Installing tunnel liner and concreting.

88th to 87th Streets

Installation of employee trailers and offices.

87th to 86th Streets

Delivery and installation of structural steel for North Muck Enclosure. Construction of North Muck Enclosure.

86th Street Between 1st and 3rd Avenue

Demobilization of center work zone. Mobilization of work zone on the South side of 86th Street for utility relocations. Reducing sidewalk on South side of 86th Street to 7 feet. Traffic will be moved to North side of 86th Street between 1st and 2nd Avenues.

86th Street North West corner Ancillary 2

Interior demolition work in preparation for excavation. Installation of support of excavation. Con Edison cable installation.

86th to 85th Streets

Maintenance and Protection of Traffic. Contractor material storage area.

85th to 84th Streets

Maintenance and Protection of Traffic. Contractor material storage area.

84th to 83rd Streets

Delivery and installation of structural steel for South Muck Enclosure. Construction of South Muck Enclosure. Installation of new sewer and water lines at 1602 Second Avenue Entrance 1 (former Tony's DiNapoli). Contractor expects to begin controlled blasting activities 2nd week in April.

83rd Street North West corner (Ancillary 1)

Excavation and installation of support of excavation in preparation for the installation of decking.

83rd to 82nd Streets

Preparation of area for dewatering equipment.

79th to 78th Streets

Concrete deliveries to tunnel utilizing center work zone. Intermittent controlled blasting in tunnel.

74th to 73rd  Streets

Operation of water treatment plant

73rd to 72nd Streets

Controlled blasting activities. Shotcrete operations in cavern.

72nd Street North West corner Ancillary 2

Contractor expects to begin controlled blasting activities 1st week of April.

72nd to 71st Streets

Contractor material storage and maintenance area.

72nd Street South East corner Entrance 3

Continuing building demolition.

71st to 70th  Streets

Contractor offices and storage area.

70th to 69th Street

Controlled blasting activities. Shotcrete operations in cavern.

69th Street North West Side Ancillary 1

Installation of deck beams and decking. Contractor expects to mobilize crane on site 3rd week of April. Controlled blasting is scheduled to begin 1st week of May.

69th Street East Side

Shotcrete operations in underground cavern.

67th to 66th Street West Side

Concrete delivery operations to underground cavern.

63rd Street North West corner

Hoisting of materials through excavation in Plaza.

63rd Street between 3rd Avenue and Lexington Avenues

Intermittent access to existing station below 63rd St.

3rd Avenue between 63rd and 64th Street

Hoisting of material through excavation in Plaza. Occupation of parking lane on West Side of 3rd Avenue.

63rd Street between 3rd Avenue and Lexington Avenue

Intermittent access to existing station below 63rd Street.

64th Street and 3rd Avenue

Installing employee changing trailers on North East corner of 64th Street and 3rd Avenue.

WORK HOURS:
MONDAY - FRIDAY, 7:00 AM TO 10:00 PM
SATURDAY, 10:00 AM TO 7:00 PM
WORK UNDER DECKING PERMITTED 24 HOURS

BE ADVISED: Con Ed, Empire City Subway and Verizon may be performing cable and gas line work outside regular SAS construction Hours. If you have additional questions, please contact Claudia Wilson at (212) 792-9716 from 9:00AM to 5:00PM Monday through Friday, or contact the 2nd Avenue Subway Hotline 24 hours/7 days a week at (646)252-2670.

TRAFFIC UPDATES

100th to 95th Streets

95th Street to 91st Streets

87th to 82nd Streets

74th to 66th Streets

63rd Street