Project Schedule
Environmental Review Process
- Issuance of a Positive Declaration on April 21, 2003
- Issuance of Environmental Assessment / Form (EAS/EAF) on April 30,
2003
- Preparation and Issuance of a Draft Scoping Document on April 30,
2003
- Public review and comment on the Draft Scoping Document, including
a Public Scoping Meeting held on June 5, 2003 with written comment period
extending to June 16, 2003
- Issuance of a Final Scoping Document in May 28, 2004
- Issue Draft Generic EIS on June 21, 2004
- Public Hearing on Draft Generic EIS was held September 23, 2004 with
written comment period extending to October 4, 2004
- Preparation and issuance of Final Generic EIS on November 8, 2004
Engineering
- Start Design Conceptual Engineering on October 1, 2002
- Start Preliminary Engineering on April 2, 2003
- Complete Preliminary Engineering on July 22, 2004
- Start Extended Preliminary Engineering on October 1, 2004
- Start Final Design on April 7, 2005
Construction
- Evaluation of Project Delivery Approaches
- Award of First Contract Package late 2007