MTA Bridges and Tunnels Construction Improvements
- Henry Hudson Bridge
- Bronx-Whitestone Bridge
- Throgs Neck Bridge
- Verrazano-Narrows Bridge
- Robert F. Kennedy Bridge
Henry Hudson Bridge
A three-year, $33 million project is underway to replace the original 1930s steel curb stringers that support the upper level roadway on either side of the bridge. In addition to replacing the stringers and installing 3,600-feet of new bridge decking, new energy-efficient roadway lighting will also be added. The new space will be re-striped, resulting in wider traffic lanes across the bridge.
| old girder being lifted out (left) and replaced by new one (right). | |
| Workers replacing the bridge's original curb stringer boxes, commonly used in the 1930s when the bridge was built, with new sub-structure steel beams, shown here being hoisted. All together there will be 30 of these steel girders installed. Each steel beam weighs 3,000 lbs. | |
Bronx-Whitestone Bridge
A 42-month, $109 million reconstruction of the Queens approach to the bridge is underway. The contract was awarded jointly to E.E. Cruz, of Manhattan, and Tully Construction Co., of Queens in July 2011. The work includes reconstruction and widening of the 1,010-foot-long Queens approach roadway and the addition of new safety shoulders. The children's playground beneath the bridge in Francis Lewis Park has already been moved from beneath the bridge and completely renovated, thanks to B&T. It reopened in May 2012.
New Piers Taking Shape
Photos by MTA Bridges and Tunnels Jeffrey Brugge
New Playground
Photos by MTA Bridges and Tunnels Jeffrey Brugge
Throgs Neck Bridge
The Queens approach of the 52-year-old bridge is being replaced under this $96.7 million contract. Main features of project include replacement of the entire concrete roadway deck, which was nearing the end of its useful life, at the Queens side of the span; rehabilitation of abutment and concrete retaining walls; and painting of structural steel including the Cross Island Parkway on- and off-ramps. More than 140,000 square feet of the roadway deck on 11 spans of the bridge in Queens are being replaced. Active construction will continue through mid-2010, with full project completion in 2011.
![]() |
![]() |
Northbound roadway in Queens under construction |
Paint removal containment operation. |
![]() |
|
| New roadway taking shape |
Verrazano-Narrows Bridge
Verrazano Toll Plaza Improvement Project
This is a $50 million, 45-month Capital improvement project that is expected to be completed in 2015. Highlights of the work include:
- A new fly-over ramp from Narrows Road South (service road) to help ease car and bus traffic onto the Brooklyn-bound upper level of the bridge.
- A new fly-over ramp at the Lily Pond entrance ramp to the bridge will be constructed to improve roadway logistics and allow smoother access for buses and cars onto the bridge's upper level.
- Construction of a new lower level connector ramp that will take motorists directly from the Staten Island Expressway to the bridge's lower level.
- Rehabilitation of the Father Capodanno entrance ramp and the Lily Pond exit ramp.
- Rehabilitation of the toll plaza roadway from the Staten Island Expressway to accommodate traffic that will be traveling through the area at highway speeds rather than toll booth stop and go conditions.
Photos by Metropolitan Transportation Authority - STV Resident Engineer Bob Kuehlewein.
Toll Booth Removal Project
On the night of Feb. 1-2, 2012, the last remaining long-decommissioned eastbound toll booths at the Verrazano-Narrows Bridge were torn down. The work is part of a $50 million Capital project to improve traffic flow through the toll plaza.
Other highlights of the project, which is expected to be completed by 2015 include:
- A new fly-over ramp from Narrows Road South (service road) will be built to help ease both car and bus traffic onto the Brooklyn-bound upper level of the bridge.
- Rehabilitation of the toll plaza roadway from the Staten Island Expressway to accommodate traffic that will be traveling through the area at highway speeds rather than toll booth stop and go conditions.
- Construction of a new lower level connector ramp that will take motorists directly from the Staten Island Expressway to the bridge's lower level.
- A new fly-over ramp at the Lily Pond entrance ramp to the bridge will be constructed to improve roadway logistics and allow smoother access for buses and cars onto the bridge's upper level.
- Rehabilitation of the Father Capodanno entrance ramp and the Lily Pond exit ramp.
Photos by Metropolitan Transportation Authority / Patrick Cashin.
![]() |
![]() |
|
|
![]() |
![]() |
|
|
![]() |
![]() |
|
|
![]() |
|
![]() |
![]() |
|
|
Paint Removal Project
Containment system wrapping the lower tower legs of the bridge is part of a two-year, nearly $19 million Capital construction project to remove old lead paint, repair and rehabilitate steel and repaint the interior and exterior of the tower legs on both the Staten Island and Brooklyn sides of the bridge. The shroud-like covering is put in place to make sure the old paint does not escape into the environment. It is then collected and disposed of in strict accordance with New York State regulations.
Bridges need to be painted in order to keep them in a state of good repair and to provide protective coating against corrosion. The Verrazano-Narrows is particularly susceptible to corrosion because of the wind patterns where it sits in New York Bay and its exposure to harsh sea and salt air. An estimated 11,500 gallons of high-performance paint, specially designed for bridges, will be used for this project.
![]() |
![]() |
VN legs paint 4: Cable and pulley system is constructed on the Staten Island tower legs in preparation for the tarps that will completely enclose the steel structure before abrasive blasting of old paint begins. |
VN Tower Legs 2: Side view of Staten Island tower leg completely wrapped in the containment system. Work began in late 2010 with actual removal of paint beginning in July 2011. |
![]() |
|
VN SI Tower Legs: View of the Staten Island tower legs under containment system taken from the Brooklyn side of the bridge. Once completed, work will move to the Brooklyn side of the bridge. |
|
RFK Bridge Planned Rehabilitation Projects
Project Overview
Through 2019 motorists can expect to see plenty of activity at the sprawling, three-complex Robert F. Kennedy Bridge as MTA Bridges and Tunnels is spending nearly $1 billion in Capital improvements. The largest projects include reconstructing the supporting bridge structures at the Manhattan and Bronx toll plazas and rehabilitating and replacing the bridge’s seven ramps.
The RFK Bridge, which opened in July 1939, includes three bridges and 14 miles of roadways that merge at a junction structure on Randall's Island where traffic is distributed to and from Manhattan, Queens and the Bronx.
Click the following tabs to see work unfolding.
Manhattan toll plaza resurfacing
Some 400,000-square-feet of old asphalt at the Manhattan toll plaza was removed and replaced with a new, rubberized asphalt to help prevent water from seeping into the concrete deck. This $5.8 million project, completed in early 2012, provides a smoother riding surface for customers and will extend the life of the roadway until full reconstruction of the Manhattan toll plaza gets underway.
| Before: Harlem River Lift Span Manhattan Plaza | After: Harlem River Lift Span Manhattan Plaza |
| During: RFK Manhattan Toll Plaza Resurfacing | After: Manhattan Plaza Striped |
The 12,000-square-foot Harlem River Drive southbound exit ramp, which leads onto the bridge at East 125th Street, was completely rebuilt. A temporary ramp was put in place while the 50-year-old ramp was reconstructed. The $12.4 million project was completed in December 2011.
- Google Translate




























































